The site’s permit (CPG #NM5959) was issued as on May 18, 2015 allowing installation late in 2016 with commissioning early January 2016.
The land is owned by Green Mountain Community Solar LLC through its subsidiary, Groton Timberworks Community Solar LLC.

Timberworks Construction

Groton Vermont

Groton Vermont

site map

Survey of land - owned by Groton Community Solar LLC.

Timberworks Soils Testing September 2015

Post Testing - Setember

Timberworks site plan

Site Plan

Nov 1 2015 Site Prior to Construction

Graded Site - October

Nov 17 Staged Racking

Posts and Racks Staged - November

Post setting Nov 18

First posts - Nov 18th

GMP Pole

GMP interconnection pole along Route 302

Nov 20 _ 1

Staged posts and racking

Nov 18_2

Gyke post impact driving machine

nov 20 3

Cap installation

nov 20 2

Racking being squared

DC Energy Trailer

Our installation contractor

first panel timberworks

The first panel - Nov 23

GMP Pole Setting

GMP sets pole - Nov 30

Pouring Concrete Dec 9

Concrete footers required on about half of the posts on the last two rows - Dec 9th

Panel Installation Complete

Panel installation complete Dec 18th

Meter Socket Dec 22

Meter socket installation Dec 22nd

Meter and Inverters Dec 28

From right: GMP Disconnect, GMP Meter, Solar Farm Disconnect, Three of seven inverters. Dec 28th

Connecting Inverters Dec 30

Two 10 kW and five 24 kW SMA inverters placed. Wires being pulled through conduits as of 2 PM Dec. 30

Working at night

Contractor working into evening to meet end of 2015 deadline.

Jan 16 PR Photo LLR

Commissioning January 2016

tw-ytd